Information from the opening of offers in the procedure organized by OGP Gaz-System SA for the supply of insulated steel pipes under the concluded Framework Agreement (FSRU project, procedure No. 4)
The Management Board of STALPROFIL SA (the Company) informs that on May 29, 2024, it received information about the result of opening by OGP Gaz-System SA (the Ordering Party) of offers submitted in the public procurement procedure for investment tasks entitled: POM1: "Gas pipelines Kolnik-Gdańsk together with the infrastructure necessary for their service in the Pomeranian Voivodeship"; POM2: "Construction of the DN1000 MOP 8.4 MPa Gustorzyn-Wicko gas pipeline, part 2, section Gardeja-Kolnik"; POM3: "Construction of the DN1000 MOP 8.4 MPa Gustorzyn-Wicko gas pipeline, part 1, section Gustorzyn-Gardeja". Proceedings No. 4 (Executive Proceedings No. 9). Procedure number: ZP/2024/04/0034/PZ. This procedure was carried out under the Framework Agreement, which the Company informed about in current report No. 34/2022 of September 30, 2022.
The subject of the order was divided into three parts. According to the information made available on the OGP Gaz-System SA Purchasing Platform, the offers submitted by the subsidiary Izostal SA (Contractor) for Parts 1 and 3, with a total value of PLN 80.3 million net, which is PLN 98.8 million gross, turned out to be the most advantageous.
The specification of essential terms of the order provides for the delivery of insulated steel pipes with a diameter of DN1000 and a length of approximately 33 km between February 1, 2025 and August 31, 2025.
The Company will inform about receiving official information about the selection of Izostal SA's offers as the most advantageous ones in a separate current report.